sticky logo DM BAU

Rosental staff restaurant

Project details

Client: SV Schweiz AG

Sector: Industry and trade

Construction systems: Solid modular construction

Construction time: 4 months

Year of construction: 2013

Architect: Gemasy GmbH

Area (m²): 411

Place: Basel

Execution as general contractor

Until now, the catering company SV Group had been able to provide its services for the companies based there in an existing infrastructure. Due to restructuring, a new solution had to be found quickly. Within a few months, we built a fully functional staff restaurant using solid modular construction technology. This offers a high-quality interim solution for the next 3 years. After that, its future use is still open.

Highlights

  • Short construction time
  • Option for disassembly
  • High quality
Are you interested in a project or would you like a no-obligation consultation? We look forward to hearing from you.